More

    Warning: Illegal string offset 'sidebar' in /home/customer/www/stocks.com.au/public_html/wp-content/themes/mining/functions.php on line 498

    Warning: Illegal string offset 'home' in /home/customer/www/stocks.com.au/public_html/wp-content/themes/mining/functions.php on line 498

    Warning: Illegal string offset 'home' in /home/customer/www/stocks.com.au/public_html/wp-content/themes/mining/functions.php on line 500

    Warning: Illegal string offset 'home' in /home/customer/www/stocks.com.au/public_html/wp-content/themes/mining/functions.php on line 504

    Warning: Illegal string offset 'sidebar' in /home/customer/www/stocks.com.au/public_html/wp-content/themes/mining/functions.php on line 516

    Warning: Illegal string offset 'home' in /home/customer/www/stocks.com.au/public_html/wp-content/themes/mining/functions.php on line 516

    Warning: Illegal string offset 'home' in /home/customer/www/stocks.com.au/public_html/wp-content/themes/mining/functions.php on line 518

    Thomson Resources positive on New England Fold Belt Hub and Spoke strategy following processing pathway study

    Thomson Resources (ASX:TMZ) has received the Central Processing Pathway Study Stage 1 Report prepared by Core Resources regarding various projects comprising the New England Fold Belt Hub and Spoke Strategy (NEFBHS).

    The company reports that number of different flowsheet and central processing options were considered for the various projects comprising the NEFBHS.

    A central processing option was settled on with satellite sites at the Mt Carrington project and the Webbs Silver project that feed into a Central Processing Facility at a new site near Tenterfield, NSW.

    The selection of a site near Tenterfield was primarily based on its proximity to the Mt Carrington project, which will have the largest resources available to a central processing facility.

    The Mt Carrington site and Webbs Silver sites would both have a crushing/grinding and flotation circuit to produce rougher concentrates to be sent to the Tenterfield site for further processing. It may also be viable to transport Silver Spur ore to the Webbs concentrator for processing. Conrad ore is envisioned to be processed at the mine site using the relocated Webbs concentrator.

    Thomson notes the central processing facility near Tenterfield includes an Albion Process plant as well as an intensive cyanidation circuit and Merrill Crowe plant for the production of gold/silver dore.

    The Albion Process plant allows for the production of higher value products from the Webbs Silver resource  and also provides a method to generate value for the zinc contained within the Mt Carrington resources if high-grade zinc concentrates cannot be produced. It may also be used for the processing of Conrad ore.

    An indicative production schedule was prepared based on a 1Mtpa Mt Carrington treatment rate and 750,000tpa Webbs treatment rate (followed by 750,000tpa Conrad treatment rate).

    The nominal project life was close to 8 years.

    Net revenue figures (using current metal prices) considering the cost of transport as well as metal payables were calculated for assumed products.

    An annual cash flow considering typical mining and plant operating costs for similar types of production plants was then prepared to provide an indication of funds available to pay back capital and generate project profits.

    Thomson projects

    This analysis showed positive cash flows. However, further engineering is required to establish the actual operating and capital costs for the project which will be completed in a formal concept study following further test work.

    “We now have a clear pathway forward as to what the New England Fold Belt Hub and Spoke Strategy will look like”

    Addressing the report, Executive Chairman David Williams commented: “Core Resources have produced a very thorough and well worked Stage 1 Central Processing Pathway Study. We now have a clear pathway forward as to what the New England Fold Belt Hub and Spoke Strategy will look like.

    The very pleasing aspect of the study is that even with using today’s current low metal prices and without expanding the resources or fine tuning the processes, the early stage indicative numbers are positive for proceeding forward with the strategy.

    Whilst I appreciate that they are only indicative numbers, to see that even at today’s prices and using only 4 of the deposits, the indicative cashflows from techno-economic evaluation estimate (before capital expenditure and capital costs) show a positive cashflow over the 8-year project life of A$334 million (using a silver price of A$28/oz), with A$206 million accumulating in the first 3 years.

    It is true that the study was less than positive about the Texas project remaining part of this strategy, and the company is now giving serious consideration to what happens with Texas.

    As we add more resources through further extensional/expansional resource drilling activities and as the metal prices, particularly silver, increase, this NEFBHS project will just get stronger.

    Core have provided a clear pathway of work for Thomson to undertake so that we can move to completing a formal concept study. We look forward to reporting progress on this work as it is implemented and completed.”

    The key projects underpinning the NEFBHS concept were strategically and aggressively acquired by Thomson in only a 4-month period from November 2020. This includes the Conrad, Webbs and Texas District silver/gold/zinc/lead/copper (tin) projects.

    Thomson has reported Mineral Resource Estimates (MREs) to JORC 2012 for the 100% owned Webbs, Conrad, Silver Spur, Twin Hills, and Mt. Gunyan deposits and restated the  Strauss-Kylo MREs (Thomson earning up to 70% interest) that contain a combined total of 22.8Mt at 119 g/t Ag-Eq for a total resource base of 87.1Moz of Ag-Eq.

    Write to Adam Orlando at Mining.com.au

    Images: Thomson Resources Limited
    Adam Orlando
    Adam Orlando
    stocks.com.au Senior Reporter Adam Orlando more than 20 years’ experience in the media having held senior roles at various publications, including as Asia-Pacific Sector Head (Mining) at global newswire Acuris. Adam has worked in newsrooms around the world including Hong Kong, Singapore, London, and Sydney.